Spokane Street Project Limits

Spokane Street Rehabilitation Project

Project Limits: Spokane Street – Intersection of Seltice Way and Spokane Street to the Spokane River Bridge

Project Duration: July-October 2024

Project Cost: $1.14 Million

  • Idaho Transportation Department Strategic Initiatives Grant Award: $1.17 Million

Project Description: 

  • Remove and replace existing asphalt surface
  • Sewer manhole repairs at intersection of Spokane Street and Seltice Way and I-90 Eastbound ramps
  • Replacement of the BNSF rail crossing and installation of utility casing underneath the rail tracks
  • Waterline, hydrant and stormwater improvements and installation of dry utilities for future use. Replacement of ADA pedestrian ramps throughout the project.
  • The Idaho Transportation Department proposed an extension of the city’s paving limits through ITD’s jurisdiction on Spokane Street to include the area between I-90 and Seltice Way. If this work is added to the Spokane Street project, additional information and schedule updates will be provided here.

Project Detours: Four stages of traffic control are designed to minimize impacts of traffic movements through the project work area. These traffic revisions will be implemented based on the type and location of work being performed.

  • Northbound work: Northbound traffic will detour on Henry Street during this phase of project work. Maintain Southbound traffic on Spokane Street during this phase of work.
  • Southbound work: Southbound traffic will detour on Henry Steet During this phase of project work. Maintain Northbound traffic on Spokane Street during this phase of work.
  • BNSF Rail Surface Improvements: All traffic will be detoured on Henry Street during this truncated phase of work.
  • Seltice and Eastbound Intersections: Manhole repair work will be performed at night, maintain one lane of traffic through the work zone.
  • Pedestrian detour will be revised throughout the project, based on the phasing of work
  • Access to local businesses and residence will be maintained throughout the project. The Henry Street detour will provide local access to businesses located along the East frontage of Spokane Street

Road Closure Map

Spokane River Bridge Project

Spokane River Bridge Project, owned by the Post Falls Highway District, includes deck surface repair and in-water superstructure repairs. This work is scheduled to begin Thursday, May 9, 2024 and is expected to last until October 2024. There will be temporary signals at each end of the bridge, and travel will be reduced to one lane during the deck phase. Work in the water will consist of boats, barges, and diving crews repairing the bridge piers. In-water signs and buoys will advise water vessels of the in-water work and direct them around the project. Hamilton Construction Company is performing the work, and Keller Associates is the consulting engineer managing the contract.

Contact Information

City of Post Falls Projects Division
Andrew Arbini, Projects Division Manager

Phone: (208) 457-3378

Office Hours:  
7:00 a.m. – 4:00 p.m.
Monday-Friday

Project Contractor: Interstate Concrete and Asphalt

Project Engineer: Welch Comer Engineers

Spokane River Bridge Project

Keller Associates, Inc.
Jeff Sorenson, PE
Project Manager

Phone: (208) 758-8601

Office Hours:  
8:00 a.m. – 5:00 p.m.
Monday-Friday